Pre-upgrade Assessment is a technical document, but above all a risk-governance tool. It translates the operational question “can we complete the upgrade within the maintenance window?” into measured numbers, not eyeballed guesses.
The four fundamental figures #
A complete assessment answers four concrete questions:
- Current sizes: how much does each database weigh today, by schema, by table, on real disk vs.
information_schemaestimate - Growth rate: how fast data grows over time, measured via historicized snapshots and/or binary log volume
- Backup times: how long a full backup takes, measured on every tool that might be used (
mysqldump,mydumper,xtrabackup,pg_dump,expdp…) - Restore times: how long it takes to rebuild the database from scratch — the most important and most frequently forgotten number
Why restore times matter more than backup times #
Backups run in the background, often outside the maintenance window. Restores instead are inside the window, inside the rollback plan, inside the service-restoration SLA. A dataset that backs up in 30 minutes may take 4 hours to logically restore: if the rollback plan doesn’t account for it, the window isn’t enough.
When to do it #
- Before a major upgrade (MySQL 5.7→8.0, Oracle 12c→19c, PostgreSQL 14→16)
- Before an infrastructure migration (new storage, new hypervisor, cloud migration)
- Before a re-platforming from on-premises to cloud
- As an annual periodic audit on production databases, to verify that measured times are still valid after data growth
What to deliver to the PM #
A single table, not thirty slides. Columns: server, current size, estimated growth, backup time, restore time (primary tool), worst-case restore time (mysqldump or equivalent). The PM should be able to attach it to the cutover plan without any rework.